SECTION 694 — BUILT-UP CURB RAMPS
694.1 DESCRIPTION —
This work is construction of a built-up curb ramp on a completed surface.
694.2 MATERIAL —
Bituminous Binder Course, ID-2 — Section 421.2
Bituminous Wearing Course, ID-2 — Section 420.2
Bituminous Wearing Course, FJ-1 — Section 422.2
694.3 CONSTRUCTION —
As shown on the Standard Drawings, as specified in the applicable parts of Section 420.3, Section 421.3 and Section 422.3 and as follows:
(a) Preparation of Surface.
Prior to placing built-up curb ramp, clean the surface on which it is to be placed, then apply a tack coat, when indicated, as specified in Section 460.3.
694.4 MEASUREMENT AND PAYMENT —
Square Yard
(a) Bituminous Binder Course, ID-2.
(b) Bituminous Wearing Course, ID-2.
(c) Bituminous Wearing Course, FJ-1.
No Supplement