SECTION 202 — DEMOLITION OR PARTIAL DEMOLITION OF BUILDINGS AND OTHER STRUCTURES

202.1 DESCRIPTION — This work is total or partial demolition of buildings or other structures, as indicated.
The following definitions apply:

(a) Total Demolition. Total demolition and removal of indicated buildings and other structures located wholly within the right of way.

(b) Partial Demolition. Partial demolition and removal of indicated buildings or other structures located partly within the right of way. Only the portion within the right of way is demolished and removed, unless the owner of the remaining portion requests and authorizes total demolition in writing.

(c) Refinishing Party Walls. Demolition of an indicated building or other structure to the party wall which separates it from another building or structure outside the right of way. The exposed portion of the party wall, including the party wall foundation, is refinished as specified.


202.2 MATERIAL —

(a) Cement, Type IS, IP, or II. Section 701

(b) Fine Aggregate, Type A. Section 703.1

(c) Lime. Section 723

(d) Water. Section 720.1

(e) Emulsified Asphalt, Class E-1 or E-2. Section 702

(f) Caulking Compound. Section 705.8

(g) Other Material. Certify as specified in Section 106.03(b)3.

Immediately before scratch coat application, wet the wall surface evenly but do not saturate. Apply a 3/8-inch scratch coat, heavily cross-hatched to integrate with the metal mesh lath.
After the scratch coat dries thoroughly, again, wet the wall surface evenly but do not saturate, and apply a 3/8-inch brown coat.
After the brown coat dries thoroughly, again, wet the wall surface evenly but do not saturate, and apply a 1/8-inch finish coat. Provide color and finish type as directed.
Protect each coat of plaster from sun and wind to prevent rapid drying. Keep each coat moist by sprinkling for at least 3 days after application or as directed. Allow each coat to dry thoroughly before placing the succeeding coat.
Upon completion of the plastering, install suitable matching wood trim along the border of the roof. Paint new wood trim to conform to the trim color of the remainder of the structure or as directed.

(f) Backfilling. Backfill subsurface areas as specified in Section 206.3 and as follows:
Before starting backfilling operations, submit the method of backfill and compaction for review and acceptance.
Furnish additional embankment material for backfilling subsurface areas. Have the quality, nature, and source of any additional embankment material accepted before use. Do not use unsuitable or unstable material in the backfill. Satisfactorily store material encountered in the demolition, which is suitable for backfill, until the walls are down.
Carefully backfill cellars and other subsurface spaces, and grade to the adjacent ground level or as directed.
Backfill and grade to ensure proper drainage. Prior to placing the first layer of backfill, break-up existing cellar floors and other surfaced areas to ensure adequate subsurface drainage.
Clean party wall foundations against which backfill material is to be placed, point brick or block walls with mortar, and waterproof with two coats of emulsified asphalt.


(g) Treatment of Disturbed Areas. Treat disturbed areas resulting from demolition with seeding and soil supplements as specified in Section 804. Use a seeding type as indicated or directed. When directed, mulch as specified in Section 805.


202.4 MEASUREMENT AND PAYMENT —

(a) Demolition. Lump Sum
If a structure is set afire, the amount bid for this item will be deducted from the total amount due.

(b) Refinishing Party Walls. Lump Sum

Most Current Supplement

BACK TO TABLE OF CONTENTS