Butler County Future Projects

SR #
Project Name
Project Length (Years)
Proposed Work
Location
Est.
Start Year*
8
Harrisville Bridge
0.28
Bridge replacement with minimal approach roadway work
Existing structure carrying SR 8 over a branch of McMurray Run in Harrisville Township
2013
8
Adams Corner Bridge
0.00
Bridge replacement
Existing structure carrying SR 8 over a tributary to McDonalds Run in Mercer Township
2013
19
US19/Freedom Rd/PA228 Int
1.49
Intersection improvements, including creation of additional turning lanes and retiming traffic signals
Intersection of US 19, SR 3020 Freedom Rd, and PA 228 in Cranberry Township
2013
38
Bridge South of Hooker
0.00
Bridge replacement with minimal approach roadway work
Existing structure carrying PA 38 over a tributary of Connoquenessing Creek in Concord Township
2012
38
Sandy Point Bridge
0.10
Bridge replacement with minimal approach roadway work
Existing structure carrying SR 38 over a tributary to Little Scrubgrass Creek in Allegheny Township
2013
38
Greece City Bridge
0.11
Bridge replacement with minimal approach roadway work
Existing structure carrying SR 38 over a tributary to Connoquenessing Creek in Concord Township
2013
58
Murrinsville Bridge #2
0.10
Bridge replacement with minimal approach roadway work
Existing structure carrying PA 58 over Murrin Run in Venango Township
2012
58
Murrinsville Bridge #1
0.00
Bridge replacement with minimal approach roadway work
Existing structure carrying PA 58 over a tributary to Blacks Creek in Marion Township
2012
58
PA 58 McMurray Run Bridge
0.00
Bridge replacement with minimal approach roadway work
Existing structure carrying SR 58 over McMurray Run in Mercer Township
2013
79
I-79/SR 422 Interchange
0.10
Bridge rehabilitation
Existing structure carrying I-79 northbound and southbound over SR 422 and Muddy Creek in Worth Township
2012
228
PA 228/I-79 Ramps
1.65
Construction of an interchange on-ramp between PA-228 and I-79
PA 228 Southbound in the Northwest quadrant of SR 8001 of the SR 8001 interchange of I-79 and PA 228 in Cranberry Township and PA 228 Northbound from approximately 700ft west of the PA 228/Mars Rd intersection to the PA 228/I-79 overlap
2012
228
PA 228 Mars RR Bridge
0.13
Bridge replacement and intersection improvements
Existing structure carrying PA 228 over the CSX/B&O Railroad with a culvert extension over Breakneck Creek south of Mars Borough in Adams Township
2012
1010
Hooker Road Bridge #2
0.52
Bridge replacement
Existing structure carrying SR 1010 Hooker Road over Bear Creek in Concord Township
2013
1027
East Unity Road Bridge
0.73
Bridge replacement with minimal approach roadway work
Existing structure carrying SR 1027 East Unity Road over a tributary to the south fork of Little Scrubgrass Creek near the Venango county line in Cherry Valley Borough
2012
2004
Kittanning St. Bridge #2
0.02
Bridge replacement with minimal approach roadway work
Existing structure carrying SR 2004 Kittanning Street over Connoquenessing Creek in the city of Butler
2013
2007
Saxonburg Trans. Enhance.
0.25
Transportation and safety enhancements including utility upgrades, line-of-sight improvements, crosswalks, ADA curb ramps, sidewalks, street lighting, and greenway buffers
Along SR 2007 West Main Street from approximately 0.19 miles west of SR 2005 Pittsburgh Street to SR 2011 North and South Rebecca Streets in Saxonburg Borough
2012
2010
Thorn Creek Bridge
0.01
Bridge replacement
Existing structure carrying SR 2010 Saxonburg Road over Thorn Creek in Jefferson Township
2012
4006
Keister Road Bridge
0.19
Bridge replacement with minimal approach roadway work
Existing structure carrying SR 4006 Keister Road over Slippery Rock Creek in Slippery Rock Township
2012
7212
T-301 Graham Bridge
0.01
Bridge replacement with minimal approach roadway work
Existing structure carrying T-301 Darlington Road over Brush Creek in Cranberry Township
2013
7217
T-325 Eidenau Bridge
0.01
Bridge replacement
Existing structure carrying T-325 Textor School Road over Breakneck Creek in Jackson Township
2012