PENNSYLVANIA DEPARTMENT OF TRANSPORTATION
ENGINEERING DISTRICT 6-0
TRAFFIC RESTRICTION BULLETIN


(NOTE: SCHEDULES ARE SUBJECT TO WEATHER CONDITIONS)
(All restrictions 24 hours/day, 7 days/week unless otherwise noted)

For current traffic and travel conditions, visit 511PA

PENNDOT ROADWAY MAINTENANCE HOTLINE: 1-800-FIX- ROAD

[PHILADELPHIA]    [BUCKS]    [CHESTER]    [DELAWARE]    [MONTGOMERY]   [ALL


previous next
Hide details for PhiladelphiaPhiladelphia
*I-95 NorthBridge Joint & Deck Repairs: LANE CLOSURES between Walt Whitman Bridge & Washington Ave. 8 PM - 5 AM.  4/27/15-5/7/15  Neshaminy Constructors, Inc.  $2.5 million
Broad St.Pothole Repair: LANE RESTRICTIONS between Chestnut St. & Oregon Ave. 8 AM - 4 PM.  4/22/15-4/24/15  James J. Anderson  $9.3 million
Cheltenham Ave.Pothole Repair: LANE RESTRICTIONS between Old York Rd. & Front St. 8 AM - 4 PM.  4/22/15-4/24/15  James J. Anderson  $9.3 million
Grant Ave.Roadwork: LANE RESTRICTIONS between US 1 (Roosevelt Blvd.) & State Rd. 7 AM - 4 PM.  4/22/15-4/24/15  James J. Anderson  $9.3 million
Ridge Ave.Paving & Manhole Adjustments: LANE RESTRICTIONS between 33rd St. & Northwestern Ave. 7 PM - 5 AM; 7 AM - 4 PM.  4/22/15-4/24/15  James J. Anderson  $4.2 million
*I-95 SouthSign Structure Installation: LANE CLOSURES near Girard Ave. Interchange. 10 PM - 5 AM.  4/21/15-4/22/15  James J. Anderson  $39 million
Benjamin Franklin Parkway N & SMedian Island Reconstruction: LANE CLOSURE between 16th St. & 17th St. 9 AM - 3 PM.  4/20/15-4/24/15  Tony DePaul & Son  $3.3 million
Columbia Ave. Bridge Construction: CLOSED & DETOURED between Richmond St. & East Wildey St. 9 AM - 3 PM. DETOUR POSTED.  4/20/15-4/24/15  James J. Anderson  $39 million
Frankford Ave.Line Striping: LANE RESTRICTIONS between Torresdale Ave. & Robbins St. 9:30 AM - 3:30 PM.  4/20/15-4/22/15  James J. Anderson  $9.3 million
Frankford Ave.ADA Ramp Installation: LANE RESTRICTIONS between Toresdale Ave. & Robbins St. 9:30 AM - 3:30 PM.  4/20/15-4/24/15  James J. Anderson  $9.3 million
Grant Ave.Milling: LANE RESTRICTIONS between US 1 (Roosevelt Blvd.) & State Rd. 7 PM - 6 AM.  4/20/15-4/24/15  James J. Anderson  $9.3 million
Holme Ave.Roadwork: LANE RESTRICTIONS between Fairfield St. & Revere St. 9 AM - 3 PM & 7 PM - 6 AM.  4/20/15-4/24/15  Buckley & Company, Inc.  $15.5 million
Holme Ave. EastRoadwork: CLOSED & DETOURED at US 1. 7 PM - 6 AM. DETOUR POSTED.  4/20/15-4/22/15  Buckley & Company, Inc.  $15.5 million
Marlborough Ave.Bridge Construction: CLOSED & DETOURED between Richmond St. & East Wildey St. 9 AM - 3 PM. DETOUR POSTED.  4/20/15-4/24/15  James J. Anderson  $39 million
New State Rd.Roadwork: CLOSED & DETOUR between State Rd. & Milnor St. 8 PM - 5 AM. DETOUR POSTED.  4/20/15-4/24/15  Walsh Construction Company  $212.3 million
PA 611 N & S (Broad St.)Trench Restoration: LANE CLOSURES between Glenwood St. & Cuthbert St. 9 AM - 3 PM.  4/20/15-4/24/15  Tony DePaul & Son  $8.6 million
Rhawn St.Line Striping: LANE RESTRICTIONS between US 1 (Roosevelt Blvd.) & State Rd. 9:30 AM - 3:30 PM.  4/20/15-4/24/15  James J. Anderson  $9.3 million
Richmond St.ADA Ramp Installation: LANE RESTRICTIONS between Ann St. & Bridge St. 7 AM - 4 PM.  4/20/15-4/24/15  James J. Anderson  $9.3 million
Richmond St.Paving: LANE RESTRICTIONS between Ann St. & Bridge St. 7 PM - 5 AM.   4/20/15-4/22/15  James J. Anderson  $9.3 million
US 1 North (Roosevelt Blvd.)Conduit Installation: RIGHT LANE CLOSED between Harbison Ave. & Southampton Rd. 9 AM - 3 PM.  4/20/15-4/24/15  Tony DePaul & Son  $5.9 million
US 1 South (Roosevelt Blvd.)Line Painting: INTERMITTENT LANE CLOSURES between Southampton Rd. & 9th St. 9 AM - 3 PM.  4/20/15-4/24/15  Tony DePaul & Son  $5.9 million
US 1 (Roosevelt Blvd.)Roadwork: LANE CLOSURE between Rhawn St. & Strahle St. 9 AM - 3 PM & 7 PM - 6 AM.  4/20/15-4/24/15  Buckley & Company, Inc.  $15.5 million
*I-676 E & WDrain Cleaning/Debris Removal: LANE RESTRICTIONS between I-76 & I-95. 9:30 AM - 2 PM.  4/20/15-4/23/15  Maintenance  
*I-676 E & WInlet Welding: LANE CLOSURE between Broad St. & I-76. 11 PM & 5 AM.  4/20/15-4/23/15  Buckley & Company, Inc.  $64.8 million
*I-76 E & WDrain Cleaning/Debris Removal: LANE RESTRICTIONS between US 1 (City Ave.) & 26th St. 9:30 AM - 2 PM.  4/20/15-4/23/15  Maintenance  
*I-95 N & S Drain Cleaning/Debris Removal: LANE RESTRICTIONS between Phila. Int. Airport and PA 63 (Woodhaven Rd.) 9:30 AM - 2 PM.  4/20/15-4/23/15  Maintenance  
*I-95 NorthRoadwork: LANE CLOSURE at Cottman Ave. Interchange. 8 PM - 5 AM.  4/20/15-4/24/15  Walsh Construction Company  $212.3 million
*I-95 North on-ramp at Princeton Ave.Roadwork: RAMP CLOSED & DETOURED. 8 PM - 5 AM. DETOUR POSTED.  4/20/15-4/24/15  Walsh Construction Company  $212.3 million
*I-95 North ramp to Cottman Ave.Roadwork: RAMP CLOSED & DETOURED. 8 PM - 5 AM. DETOUR POSTED.  4/20/15-4/24/15  Walsh Construction Company  $212.3 million



previous next